Empty project default scope 5.0
-
Ciairo
- Posts: 30
- Joined: Sun Dec 11, 2016 11:40 am
Empty project default scope 5.0
Hi, I would like to save a new default empty project on scope software v.5.0 how should I do? Thanks!
- garyb
- Moderator
- Posts: 23474
- Joined: Sun Apr 15, 2001 4:00 pm
- Location: ghetto by the sea
Re: Empty project default scope 5.0
set\settings\projects\save project as default.
"save project as startup" is for the project that Scope opens with.
"save project as default" is for the project that opens when you click on file\new.
"save project as startup" is for the project that Scope opens with.
"save project as default" is for the project that opens when you click on file\new.
-
Ciairo
- Posts: 30
- Joined: Sun Dec 11, 2016 11:40 am
Re: Empty project default scope 5.0
Thank you very much! Best regards! Claudio